Wednesday 28 June 2017

28th June. Meeting with Howard Sellers & Stew Chandler to decide on final agreed list of works re heating and air conditioning.  This has now been agreed and a contractor will now be appointed to work with the builder on the main works. DM
Building start date should be August 14th.  A pre meet with the builder and architect is being held on 4th July to sign the contracts. There is now other work being planned to support the main works to ensure that the works can take place on time and in a safe environment for club members.  DM.

Ladies Changing Room is Growing!

The walls have come down and the new enlarged space looks great as it extends into the old bar store.